top of page

Overview of some of our recent projects

Delta Airlines

Delta Airlines

Expansion joint replacement at a parking deck of Delta TOC.

Three Ravinia

Three Ravinia

Atlanta, GA This office tower had a large opening in an office space between the second and third floor. A new tenant moving into this space requested this opening to be filled in. We placed around 16 yards of concrete, by moving it from the loading dock, up in the elevators to the third floor. Existing office space needed to be protected, to prevent damage. The concrete pour was performed on the weekend so there was no disturbance to the existing tenant.

Marta Systemwide UPS

Marta Systemwide UPS

Atlanta, GA The existing GAP Breaker station required maintenance repairs. We performed epoxy injections in existing wall cracks, resealed corners, door and window frames.

Ponce City Market

Ponce City Market

Atlanta, GA This downtown mixed development required a new stair between the 7th and 8th floor. We saw-cut and removed the concrete from the 8th floor to the loading dock area, after which we installed several structural steel beams in order to reinforce the existing structure in accordance with the engineer's requirements.

Suntrust Plaza, Atlanta

Suntrust Plaza, Atlanta

A law firm moving into the 36th and 37th floor of this office tower wanted to create a new stair between the two levels. We saw cut and reinforced this new opening in structural concrete slab.

KSU Stadium

KSU Stadium

Kennesaw, GA A design flaw in the original construction created stresses on the existing railing around the podium slab. We cut out sections of the existing topping slab, installed expansion joints and re-poured the topping slab. In addition some modifications were made to the existing steel railing, requiring in-field welding and steel fabrication. The existing gutter system around the podium was re-waterproofed, using a liquid applied material.

Church of the Apostles

Church of the Apostles

Atlanta, GA This landmark church along I-75 has two existing pre-cast parking decks, requiring immediate and maintenance repairs. We performed crack repair, epoxy injection, spall repairs, steel connection plate refinishing, spandrel panel repairs, corbel repairs, expansion joints and re-caulking/sealing.

550 Pharr Road

550 Pharr Road

Atlanta, GA This existing office tower needed maintenance repairs to the exterior. We re-caulked joints, installed epoxy bolts for new light poles, installed a new expansion joint and performed several other maintenance items.

Bekaert Corporation

Bekaert Corporation

Rome, GA The water treatment building on this industrial plant needed concrete repairs. The existing concrete beams, supporting equipment had far progressed deterioration. We chipped out all deteriorated concrete, re-formed and re-poured the existing beams, then applied carbon fiber reinforcing to the beam, avoiding future deterioration. After all work was complete, we applied sealant coating to all repair work.

Piedmont National

Piedmont National

Atlanta, GA An existing office building was renovated for Piedmont National to expand their existing space. Due to ADA requirements, this new building needed a handicapped ramp and entrance. We placed and poured this new ramp, including 50 ft of sidewalk.

bottom of page